Queensgate Keeps Adding Drive-Throughs. Duportail's Roundabouts Are Still Waiting on 2027.

November 12, 2026

"I think we're in really good shape at this point," Richland public works director Carlo D'Alessandro told the Tri-Cities Area Journal of Business in August 2025, days after the Richland Costco opened at 3125 Queensgate Drive. "We'll have the right improvements done and people will be able to get to Costco or any of the other businesses ... with limited delay."

At the time, the plan was for the Duportail Street improvements to go out to bid around February or March 2026. Construction would take about six months, so the work could have been finished by late 2026. D'Alessandro also said that moving utilities or buying property could cause delays.

Late 2026 is here, and Duportail looks the way it did the week Costco opened. The state's target schedule now puts construction approval at the end of April 2027. Meanwhile, the businesses proposed for Duportail are designed around double drive-through lanes and car stacking, and they are going through city review before the road rebuild has been bid.

A One-Year Wait Is Now Closer to Two

The project covers about two-thirds of a mile of Duportail between Keene Road and Queensgate Drive. That stretch carries an average of 19,388 vehicles a day, according to the Washington State Transportation Improvement Board's project dashboard. The city estimated that Costco alone would add 450 more cars a day to the Queensgate area at peak evening hours.

The city's own project page shows where the schedule slowed.

Milestone

Status

Costco opens

Aug. 8, 2025

Design consultant contract signed

May 6, 2025

60% plans submitted, right-of-way firm hired

October 2025 update

90% plans under city review

December 2025 update

Latest posted status

April 2026, still acquiring right-of-way

State target for bid authorization

March 31, 2027

State target for construction approval

April 30, 2027

State target for project closeout

Oct. 30, 2027

The 2027 dates are targets, not commitments. In an October 2026 interview with the Tri-Cities Area Journal of Business, Richland economic development director Mandy Wallner described the roundabouts this way: "I'm not sure of the timeline, but it is happening." If the targets hold, the 2026 holidays will be the second holiday shopping season with Costco running on the old Duportail layout. The first season on the finished road would be the 2027 holidays.

What Opened While the Plans Were in Review

The businesses that opened in Queensgate this year mostly added to the area's existing retail rather than reshaping it.

  • Cold Stone Creamery opened at 2560 Queensgate Drive in August. It shares a strip with Kadlec Express Care and Sake Express Sushi & Teriyaki, near an STCU branch and Spanky's car wash. Local owner Jay Takhar runs it.
  • Ground Support Coffee opened its third location at 2210 Keene Road in August. It joins the company's shops in Pasco and Kennewick and opens at 5 a.m. on weekdays.
  • AutoZone added a Richland store at 2851 Queensgate Drive this fall. It's open 7:30 a.m. to 9 p.m. Monday through Saturday and 8 a.m. to 8 p.m. on Sunday.

All three are walk-in businesses that fit into existing buildings or lots. The projects on deck are built differently.

The Next Tenants Are Built Around a Line of Cars

The 7 Brew Drive Thru Coffee stand under consideration for 3160 Duportail Street is the clearest example. As of September, no permits had been filed. City documents describe a building of about 510 square feet on a parcel of roughly one acre. It would have a double drive-through with room for 24 cars to queue and just 10 parking stalls, as the Tri-Cities Area Journal of Business reported in September. Idaho Central Credit Union, which has a branch next door, bought the parcel for $1.7 million on Aug. 7. The Arkansas-based chain is also looking at a site off George Washington Way next to Panda Express. As of October it had no locations in Washington.

Chick-fil-A applied in May to build at 3255 Duportail Street. The plans call for a 5,087-square-foot restaurant with a double drive-through, at a construction cost of a little over $1 million. As of mid-October, no permits had been issued. The site is part of about 10 acres at the corner of Duportail and Keene Road owned by the Kennewick Irrigation District, and environmental review filings show that land being split into seven new commercial lots. Wallner described where the plans stood to the Journal of Business:

"They have a site and they're still trying to work through how close to the intersection you can have driveways."

Controlling where cars can turn on and off this stretch is the main goal of the Duportail redesign. So a restaurant whose design depends on drive-through flow is working out its driveways on the same street the city is redesigning.

Back on Queensgate Drive, KAPP-KVEW reported the groundbreaking of Sunset Ridge Square at 1000 Queensgate Drive. It's a commercial center of more than 14,000 square feet for restaurants, service businesses and other tenants. One restaurant has signed on, and the first phase is expected to open in early 2027. The state's target for approving road construction is the end of April 2027.

The 2025 traffic analysis expected this. D'Alessandro said then that more development would follow on the state Department of Natural Resources land around Costco, and that the road work was meant to carry that traffic too. The city's project page says the corridor work is needed because of traffic growth from development on that DNR property.

What Duportail Will Look Like When It's Done

According to the TIB project record and the 2025 reporting, the finished stretch between Keene Road and Queensgate Drive will include these changes.

  1. A roundabout at Duportail and Kennedy Road, with extra turn lanes at that intersection.
  2. A second roundabout at the Vintner Square driveway, where shoppers cross between the Walmart and Target parking lots.
  3. A median from Keene Road to Queensgate Drive, which blocks left turns between the two roundabouts.
  4. Extra lanes and changes to the traffic signals at Queensgate and Duportail.

The Vintner Square roundabout was not originally part of Costco's traffic needs. The city added it because of that driveway's track record. D'Alessandro described it to the Journal of Business as "a high-capacity driveway with a lot of vehicles and a lot of crashes associated with that driveway because of impatience with drivers making turns." He said the finished improvements should last about 20 years before needing changes.

The funding package has grown as well. Reporting in 2025 described a $5.2 million project. The city's page now lists more than $6.2 million from transportation impact fees, a state Transportation Improvement Board grant, Benton County Rural Capital funds and real estate excise tax. Costco paid nearly $1.1 million in traffic impact fees for the warehouse and almost $470,000 more for its fueling station.

This Holiday Season Runs on the Current Road

Some of the routing around Queensgate already exists, because Costco built it on its own 29.48-acre site. It extended Queensgate Drive along the north side of the warehouse property, created the north-south Kingsgate Drive, added turn lanes on Kennedy, and put speed humps on Truman Avenue, the road behind Target, to discourage cut-through traffic. The Kennedy-Duportail and Queensgate-Duportail intersections were outside Costco's scope, and that's the work still waiting.

Smaller projects are working around the edges. The city's construction and traffic delays page for Nov. 6 to 13 lists City View Drive as closed from the Duportail intersection to just north of the Benton County Emergency Management building, plus part of Truman Avenue, for the City View and Truman buildout. The detour runs along Queensgate and Duportail. The same notice lists paving at Keene and Queensgate, with lane restrictions on Queensgate south of Keene. The next scheduled impact is a closure of the eastbound Keene Road left-turn lane onto northbound Queensgate. The city says the page is updated as conditions change, so it's the place to check before a Saturday trip to Costco or Target.

For now, Queensgate is getting busier faster than its main street is being rebuilt. Sunset Ridge Square's first phase is expected in early 2027, and the Chick-fil-A and 7 Brew proposals for Duportail are in city review with no opening dates. Both proposals are designed around double drive-through lanes on a street where the median and roundabouts are still targeted for 2027.

If you live near Queensgate and are wondering how two years of construction and a stretch of new drive-throughs might affect a sale or a move nearby, Caroline Couture Homes is glad to go over what's on the corridor's calendar and how buyers are likely to see it. A free home valuation is a calm place to start.